Background
The existing route from the village hall to the play area required visitors to walk across an open field, which often became muddy and difficult to use during the winter months. To improve accessibility and safety, a new tarmac footpath was requested by the client.
Construction Details
-
Footpath dimensions: approx. 100m long x 1.2m wide, with a total area of 122sqm
-
Ground marked out and levels checked before excavation
-
Topsoil removed using a digger and set aside for muckaway
-
Concrete edgings installed along both sides of the path on a concrete bed
-
Sub-base of MOT Type 1 compacted to 100mm on geotextile membrane
-
Tarmac applied in layers and compacted to specification
-
Additional section of path installed to link footpath into the village hall
-
All surrounding areas made good for a neat, finished appearance
Outcome
The completed footpath provides a durable, all-weather route from the village hall to the play area, eliminating the need for foot traffic to cross muddy grass. The new path has improved access for parents, children, and hall users year-round and blends neatly with the surrounding landscape.